Kitchen Renovation
ABC Building Ltd · BS8 2LR · In progress
Project record
Current recorded total
£19,650
Pending changes are not included in your recorded total until you record them as agreed.
Needs attention
Something changed?
Upload the message, screenshot or document. BuildRecord looks for a possible project change — you decide what gets recorded.
Recent activity
Invoice reconciliation completed
£2,250 unreconciled
Final invoice uploaded
ABC Final Invoice.pdf — £21,900
Possible project change detected
WhatsApp_18Nov.png — £1,800 requested
Variation #003 recorded as agreed
Damaged joists +£690
Final invoice
Final project check
£2,250 needs checking
We couldn't currently reconcile £2,250 of this invoice with the project information recorded in BuildRecord.
Line by line
Original contracted works
£18,400Matches your confirmed baseline.
Tile upgrade
£320Matches Variation #001, recorded as agreed on 24 October.
Additional electrical outlets
£240Possible match found — you haven't confirmed it yet.
Possible match found
Variation #002 — Add 4 double sockets, £240
Joist repairs
£690Matches Variation #003, recorded as agreed on 8 November.
Additional carpentry
£1,800No matching recorded agreed variation found.
Waste removal
£450Your baseline records waste removal as included in the original quotation.
Questions to clarify
Please provide the details associated with the £1,800 additional carpentry charge.
Please clarify the £450 waste-removal charge because my project record currently records waste removal as included.
BuildRecord helps you organise information about your project and compare your records. It does not provide legal, surveying, quantity surveying, financial or construction advice and does not determine whether an amount is legally payable. AI can make mistakes — always check important information against your original documents.